Upon completion of the installation, main line must be inspected via CCTV. Contractor can choose to have the District or an approved Private TV contractor perform the CCTV inspection. The results of the inspection must be submitted to the District for review and approval. District inspector will provide the contractor with a punch list of items that need to be corrected; the sewer system is surveyed and pre pave record drawings are prepared by the Engineer and submitted for approval. Other steps in the process:
- Once pre-pave record drawings are approved, contractor is released to finish paving.
- Final record drawings are shot to acquire actual finish grade of the rim elevation of all manholes and appurtenances.
- The physical acceptance letter will be issued.
- Contact the District to schedule removal of the sewer plug.
- Sewer plug deposit will be refunded, if applicable.